Home > Corporate News


Assembly-type Factory Building For a World-Top-500 Company Completed

In March 2017, Great Golden Horse entered a contract with M+W Group to supply concrete PC components for the extension of Intel Dalian FAB building, and Derui Shengxing undertook the production and delivery of these components. The project has a total construction area of 126,000 square meters with a precast rate of 95%. The contract subject included 1,057 columns, 1,114 beams, 507 walls, 1,809 waffle slabs, 955 DT slabs and 64 ST slabs. By Oct. 28th, the project has been completed with quality and timeline meeting the Client’s satisfaction!




LINK:ALIAN GREAT GOLDEN HORSE INFRASTRUCTURE CO.,LTD.